Updates
Latest updates

Rock breaking and blasting in the Fannborg area
No blasting will begin until mid-November at the earliest. Read more ...

Oil tanks at Hamraborg 12 will be removed
Two underground oil tanks in the parking basement at Hamraborg 12 are empty ... read more ...

Closure of westbound lane on Digranesvegur
Closure of westbound lane on Digranesvegur - read more....

Fannborg area: Groundwork has begun and preparations for blasting are underway
Construction work on the Fannborg plot is progressing, and excavation work has begun in the area. Read more....
Finishing touches on the ramp on the east side of Hamraborg are in the final stages
Work is underway on the final finishing touches on the exit ramp on the east side of Hamraborg at Vallatröð, and it is expected... Read more...

Changed access to the construction area in Kópavogur town center
The work site plan for Traðarreitur has been approved. Consequently, changes to the access to the construction area will take effect. Read more....

Lok niðurrifs á Fannborgarreit
Niðurrif á Fannborgarreit er á lokastigi. Vegna ófyrirséðra bilana... Lesa meira....

Groundworks on the Fannborg Plot
At the turn of the month August/September, earthworks will begin at the Fannborg site. Information regarding blasting - read more....

Demolition completed in Fannborg
Rock breaking is expected to finish by August 20, and the removal of materials by August 26. Read more....

West Traðarreit Plot
Demolition of the western Traðarreit area is underway. Read more...

Construction work continues on the Fannborg site
Construction work on the Fannborg plot continues, although there have been some delays in the demolition process. Read more....

The exit ramp from the Hamraborg parking garage at Vallatröð will be closed temporarily due to construction
The exit ramp from the Hamraborg parking garage onto Neðstutröð will be temporarily closed from 29 July to approximately 15 August due to modifications. Read more...